Important Announcement
PubHTML5 Scheduled Server Maintenance on (GMT) Sunday, June 26th, 2:00 am - 8:00 am.
PubHTML5 site will be inoperative during the times indicated!

Home Explore recent projects

recent projects

Published by chris.mcfadden, 2016-10-20 20:29:47

Description: recent projects

Search

Read the Text Version

LYTTELTON PORT OF CHRISTCHURCHCQ2 CONTAINER WHARFGENESIS PROJECTS SERVICES PROJECT DESCRIPTION • Management of -  Pre-feasibility and Feasibility Studies LPC’s Cashin Quay 2 container wharf was destroyed during the 2010 and  Design 2011 Christchurch earthquakes. The replacement wharf is a 230m long 34m  Procurement wide structure designed for a berth pocket for 14.5m draught vessels.  Construction • Engineer’s Representative to main The most challenging aspect of this project was that following the award of construction contract the wharf construction contract, based on a 24m wide wharf design, which • Project closeout and transfer to was constrained by LPC’s insurance negotiations, an insurance settlement Operations was reached and LPC was able to radically alter the design to better align with it business goals. In order for PC to maintain the confidence of existingPROJECT TIMELINE and prospective customers the project team was required to redesign the • March 2012 - December 2015 wharf and renegotiate the main construction contract without delay to the programmed start date. In fact construction commenced before the plannedVALUE start date of the originally tendered scope of works, with the main contractor • Project - $88M required to commence with design only partially completed.MAIN CONTRACTOR and CONSULTANT The project site was in the middle of a busy operating port and the project • HEB Construction team was required to liaise intensively with Operations to minimise business • Opus International Consultants disruption and to progressively handover completed sections of the wharf for the berthing of container vessels.Contact  Derek McFadden  Mob: + 64 [0]27 22 66 414  Email: [email protected]

LYTTELTON PORT OF CHRISTCHURCHWHARF AND SEAWALL STABILISATION TRIALGENESIS PROJECTS SERVICES  PROJECT DESCRIPTION   Management of ‐   ECI design‐build procurement process  LPC’s Cashin Quay 2 container wharf was destroyed during the 2010 and  Ground stabilisation trial  2011 Christchurch earthquakes. LPC needed to replace this structure with a  Engineer’s Representative to trial contract  seismically resilient container wharf that allowed for the berthing of 14.5m  Project closeout  draught vessels. However, insurance constraints at the time meant that the proposed new wharf could be no wider than the original wharf. To meet these  requirements LPC needed to substantially improve the stability of the edge ofPROJECT TIMELINE  the Cashin Quay reclamation and this required specialist international engineering and construction expertise.  October 2012 – April 2014   As there was no similar project experience in New Zealand, the project team selected an Early Contractor Involvement design-build project deliveryVALUE  approach. Following a Registration of Interest and Expression of Interest  Contract ‐ $3.4M  process two USA based contractor teams were selected to participate in an ECI process and to deliver tenders for both trial and production works. Raito  Inc. was awarded the contract to undertake the works using Cement Deep Soil Mixing (CDSM) with its single auger RAS column system.CONTRACTOR and CONSULTANT   Raito Inc   Opus International Consultants  Following completion of a successful trial, the contract was terminated when LPC reached an insurance settlement and was able to alter the design of the wharf to a 34m wide structure with flatter batter slope, thereby avoiding the requirement for stabilisation of the reclamation materials at depth.Contact  Derek McFadden  Mob: + 64 [0]27 22 66 414  Email: [email protected]

LYTTELTON PORT OF CHRISTCHURCHCQ1 EARTHQUAKE REPAIRSGENESIS PROJECTS SERVICES PROJECT DESCRIPTION • Management of -  Design The 22nd February 2011 earthquake came close to completely destroying  Procurement Lyttelton Port of Christchurch’s coal loadout capability and creating severe  Construction disruption to the West Coast coal export trade. Earthquake damage was such • Engineer to main construction contract that the coal ship loader was stranded at midpoint on the wharf requiring a total replacement of its support structure.PROJECT TIMELINE • February 2011 – February 2012 Temporary repairs were undertaken enabling fixed point ship loading to recommence within 21 days of the earthquake; and works commenced on aVALUE new ship loader support structure. Works were well advanced when the 13th • Project - $24M June earthquake again disabled the loadout system. A temporary support structure was erected within three weeks of the earthquake, enabling fixedMAIN CONTRACTOR and CONSULTANT point ship loading to re-commence. The 13th June event caused damage to • HEB Construction the contract works requiring a redesign of the permanent support structure. • Opus International Consultants By late 2011, coal ship loading was restored to pre-earthquake levels. This project involved a rare compression of multiple project stages into a few months: design, contract documentation and construction ran in parallel; coal loading continued within metres of construction works; and the works were tested by a significant earthquake during construction.Contact  Derek McFadden  Mob: + 64 [0]27 22 66 414  Email: [email protected]

SOLID ENERGY & LYTTELTON PORT OF CHRISTCHURCH (LPC)COALTRANS PROJECT / COAL STOCKYARD EXPANSION PROJECTGENESIS PROJECTS SERVICES  PROJECT DESCRIPTION   Management of ‐  The CoalTrans project was initiated by Solid Energy in response to its 2008  CoalTrans project Pre‐feasibilty study  long term forecast of a requirement to increase the capacity of its export coal including supply chain logistics modelling  supply chain from 2.5 Mtpa to over 4 Mtpa. A pre-feasibility study identified a  CSEP Stage 1 design, procurement and  three stage development of LPC’s coal stockyard, the Coal Stockyard construction  Expansion Project (CSEP), as follows:  CSEP Stage 2 feasibility study   CSEP Stage 1: Replacement of existing stormwater treatment  CSEP Stage 3 environmental consenting  system with a smaller footprint lamella treatment system; upgrading  Engineer’s Representative for CSEP Stage 1  coal dust mitigation measures; and installing a surface feeder to provide an additional coal loadout location and better stockpile and construction contracts  yard utilisation. These works were completed in March 2012.  Documenting CSEP Stage 2 business case    CSEP Stage 2: Cutback of the northwest wall of the coal stockyardPROJECT TIMELINE  and relocation of the export conveyor. Following completion of the  2009 – 2012  Stage 2 Feasibility Study and a significant downturn in markets this  stage was cancelled in early 2012.VALUE   CSEP Stage 3: Reclamation in Te Awaparahi Bay with additional  Stage 1 capital cost ‐ $5M  coal stockpiling. Resource consents were notified and public  Stage 2 estimated capital cost ‐ $26M  submissions received before the application was withdrawn in February 2012 as a result of the market downturn. CONTRACTOR and CONSULTANT   Opus International Consultants – engineering design   OCTA Associates – Stage 3 consenting   GHD – supply chain simulation modelling   Calcon and Filtec – Stage 1 construction Contact  Derek McFadden  Mob: + 64 [0]27 22 66 414  Email: [email protected]

SOLID ENERGY NEW ZEALAND LTDPROGRAMME OFFICE & CAPITAL INVESTMENT SYSTEMGENESIS PROJECTS SERVICES  PROJECT DESCRIPTION   Start up and development of Programme  Office (PO)  In 2001 Derek McFadden commenced a contract with Solid Energy to  Secondment of Programme Director  establish a Programme Office to oversee key organisational, engineering,  Development of Project Management and  environmental, energy and mining projects required for its long term growth. Capital Investment Systems  This contract eventually involved Derek, as Programme Director, developing  Project management training  and implementing a Project Management System throughout Solid Energy;  Development of project execution plans  participating in the planning, execution and control of projects; and training for major mining investments  and coaching Solid Energy staff in project and programme management.  Management of feasibility study and  documenting business case for  Key challenges that the Programme Office had to address were: alignment of replacement of Stockton mine aerial  project planning and execution with Solid Energy’s key business value ropeway  drivers; integration of project management with all other business processes; and the formation of project teams across multiple organisations and  geographic locations.PROJECT TIMELINE  Other tasks included:  2004 – 2008 (Genesis Projects Limited)    A major revision of Solid Energy’s stage-gate approval guidelines, which is its major capital investment portfolio management tool.  A significant review of Solid Energy’s rehabilitation liabilities and rehabilitation planning and management.Contact  Derek McFadden  Mob: + 64 [0]27 22 66 414  Email: [email protected]


Like this book? You can publish your book online for free in a few minutes!
Create your own flipbook