PROPOSED IN LA & RR COLONIES u All new villages established for resettlement of the displaced persons shall be provided with suitable transport facility which must include public transport facilities through local bus services with the nearby growth centres/urban localities u Burial or cremation ground, depending on the caste-communities at the site and their practices u Facilities for sanitation, including individual toilet points u Individual single electric connections (or connection through non-conventional sources of energy like solar energy), for each household and for public lighting u Anganwadi’s providing child and mother supplemental nutritional services u School as per the provisions of the Right of Children to Free and Compulsory Education Act, 2009 (35 of 2009) u Sub-health centre within two kilometres range u Primary health centre as prescribed by the Govt. of India u Playground for children u One community centre for every hundred families 45
INFRASTRUCTURE AMENITIES PROVIDED / u Places of worship and chowpal / free platform for every fifty families for community assembly, of numbers and dimensions consonant with the affected area u Separate land must be earmarked for traditional tribal institutions u The forest dweller families must be provided, where possible, with their forest rights on non-tinber forest produce and common property resources, if available close to the new place of settlement and, in case any such family can continue their access or entry to such forest or common property in the area close to the place of eviction, they must continue to enjoy their earlier rights to the aforesaid sources of livelihood. u Appropriate security arrangements must be provided for the settlement, if needed u Veterinary service centre as per norms 46
PROPOSED IN LA & RR COLONIES 47
Status of LA and R&R Land Acquisition u Land required for the overall project up to FRL +45.72 m is 1,67,339.13 ac., out of which 1,06,550.69 ac. is coming under submergence including headworks in which 32,888.52 ac. in West Godavari district and 73,662.17 ac. in East Godavari district. u Out of 1,06,550.69 ac., the land under submergence, 76,299.63 ac. required up to EL +41.15 m, in both districts, the entire land has been acquired leaving a balance of 491.71 ac. in Devipatnam Mandal. u The balance land with regards to submergence in between EL +41.15 m to EL +45.72 m under Plan ‘C’ and land for canal distribution system (presently survey & investigation works are in Progress) needs to be acquired. 48
Rehabilitation & Resettlement u Total 1,06,006 PDFs, have been planned to resettle in 213 R&R colonies (51 in WG & 162 in EG). u Out of the above total PDFs, 20,946 PDFs coming under EL +41.15 m are planned to shift to 77 R&R colonies (26 completed colonies and 51 ongoing colonies) and balance 85,060 PDFs coming between EL +41.15 m & EL +45.72 m have been planned in 136 R&R colonies. u Out of 20,946 [3,780 in completed colonies + 3,228 One Time Settlement (OTS) + 13,938 in ongoing colonies] PDFs, 6,351 PDFs have been shifted (3,780 PDFs to 26 completed colonies & 2,571 PDFs in ongoing R&R colonies) and 3,228 PDFs have opted for OTS/Self Construction. u The status of 13,938 sanctioned houses is: v 7,667 (55%) houses with toilets have been completed, v 703 (5%) houses completed & toilets in progress, v 2,434 (17.5%) houses in advance stage (i.e. slab and above), v 1,993 (14.3%) houses are at initial stage (i.e. below slab level) & v 1,141 (8.2%) houses are not started u In addition, 3,989 PDFs have voluntarily shifted into 7,667 completed houses to whom R&R entitlements are yet to be paid. 49
EXPENDITURE DETAIL Rs. in Crores 18,434.11 Particulars 13,596.33 Total Expenditure incurred up to 31.10.2021 11,492.16 Expenditure incurred after declaration as National Project up to 31.10.2021 Central assistance released upto date after declaration of National Project Upstream cofferdam ( June 2021) 50
E-Saddle Dam Polavaram Left Main Canal - Package:1 Right Main Canal @ km 82.500 (Nov 2018) 51
CHALLENGES IN COMPLETION OF PROJECT u River Diversion through Approach channel-Spill channel, during construction period, year 2019-2021 u Rehabilitation & resettlement of 1,05,601 Project Displaced Families (PDF) in Andhra Pradesh due to reservoir submergence u Decision on reservoir submergence action plan v Either Construction protective embankments in river Saberi & Sileru along with infall, outfall & pumping arrangement in the territories of Odisha & Chhattisgarh v Or LA and RR package for 1002 PDFs of Odisha and 2335 PDFs of Chhattisgarh u Construction of cut-offs (Plastic Concrete Diaphragm Wall, Jet grout columns) below the river bed for building earth cum rock fill dams across Gap-I and Gap-II u Ground improvement works through innovative methods (viz., Vibro floatatio of sand, vibro-stone columns & deep soil mixing) in the river bed at dam bases across Gap-I and Gap-II 52
View of the access road to upstream cofferdam in Photo showing jet grouting activity in progress front of reach 3 (Jun 2021) (Jul 2018) Vibro Compaction of Sand at ECRF Dam across Gap-II Distance of habitations to Tadwai R&R Colony (Apr 2019) 53
CHALLENGES IN COMPLETION OF PROJECT u Fabrication & erection of 48 Hydraulic Hoist Radial Gates (15.96 m × 20.83 m) and 20 River Sluice Vertical Gates (2.1m × 3m) u Bed and Slope protection works of 2.92 km long and 1 km width Spill Channel u Dewatering/de-silting from Spill Channel after monsoon during construction phase in 2020 and 2021 Visit of CEO, PPA to R&R colony 54
Sand Blasting of Skin Plate on downstream of View of the Spill Channel (May 2021) Leaf of Radial Gate for Spillway (Sep 2020) Excavation at Spill Channel (May 2021) Erection Radial Gate 55
Completed Components of Polavaram Irrigation Project Headworks u Spillway (1128.40 m long, PMF 50 Lakh cusecs) substantially completed u Erection of 42 Radial Gates (16 m x 20 m) out of 48 gates u Erection of 10 sets of Service gates & Emergency gates of River Sluice Blocks substantially completed u Upstream Cofferdam substantially completed u Concrete Dam NoF Blocks in Gap III substantially completed u River Diversion through Spillway since June 10, 2021 Canals u Right Main Canal – 178.81 m long (Discharge at Head – 566 cumecs, width at head 85 m), substantially completed 56
Aerial View of the Project 57
RECOGNITIONS & RECORDS “Best Implementation of Water Resources Project” by Central Board of Irrigation & Power (CBIP) during 2019. Cement Concreting 58
Preparatory works for concreting “Largest Continues Concrete Pour” and “Most Concrete Continuously poured in 24 hours” with a record of 32,315.5 cubic metre in 24 hours by Guinness Book of World Records on 7th January, 2019 59
SPILLWAY View of Spillway Bridge from Left Flank (May 2021) 60
Spillway from Upstream side (Jul 2020) 61
SPILL CHANNEL View of the Spill Channel (May 2021) 62
Cement Concreting in Panel L 197/3, EL +8.445 m of Spill Channel (Jun 2020) 63
ECRF Dam at Gap-II Vibro Compaction of Sand at ECRF Dam Across GAP-II (Apr 2019) 64
Vibro Compaction at downstream of diaphragm wall of proposed dam base across Gap-II (Mar 2020) 65
COFFER DAMS Jet Grouting Columns of Upstream Cofferdam (Nov 2018) 66
Photo showing jet grouting activity in progress (Jul 2018) 67
ECRF DAM IN GAP-I View of alignment ECRF Dam across Gap-I from left flank (May 2021) 68
Concreting in Guide Wall for Diaphragm Wall of Gap-I ECRF Dam (Sep 2020) 69
RIGHT CONNECTIVITIES (P-62) View of P-Head Regulator of Package-62 under Right Connectivity (May 2021) 70
View of E-Saddle Dam of Package-62 under Right Connectivity (May 2021) 71
CONCRETE DAM IN GAP-III & POWER HOUSE View of Gap-III NOF Concrete Dam from left flank (May 2021) 72
Excavation of rock at Ch. 270 m, EL +87 m of Power House (Jun 2020) 73
RIGHT MAIN CANAL View of Right Main Canal @ Km 82.500 (Nov 2018) 74
View of SLRB @ Km 84.840 of Right Main Canal (Nov 2018) 75