Important Announcement
PubHTML5 Scheduled Server Maintenance on (GMT) Sunday, June 26th, 2:00 am - 8:00 am.
PubHTML5 site will be inoperative during the times indicated!

Home Explore SOWPARBUZZ - VOLUME 1, ISSUE 5, JUNE 2019

SOWPARBUZZ - VOLUME 1, ISSUE 5, JUNE 2019

Published by Sowparnika, 2019-06-21 08:12:56

Description: A MONTHLY NEWSLETTER BY SOWPARNIKA

Keywords: SOWPARNIKAPROJECTS&INFRASTRUCTUREPVT.LTD,PROJECTUPDATES,SOWPARBUZZNEWSLETTER,SOWPARNIKANEWSLETTER,SOWPARBUZZ

Search

Read the Text Version

SOWPARBUZZ ..It’s being loved A POSITIVE ATTITUDE CAN MAKE DREAMS COME TRUE. Volume. 01 | Issue. 05 | June. 2019 www.sowparnika.com

01 Volume. 01 | Issue. 05 | June. 2019

Everything starts with you. When Sowparnika Projects and Infrastructure Pvt. Ltd. began in 2003, we were a few people in a small facility, with hopes and visions, positive and high. The driving thought behind Sowparnika has always remained “A home for all”. As the demand for quality housing in our country is always on the rise, with our sincere efforts and honest attempts, we have gradually developed and have delivered not just any home but a home that provides comfort, convenience, value for money and most importantly filled with happiness to last a lifetime. Since then, we have become one of the fastest growing companies providing quality homes across South India. Sowparnika is not just any other real estate company. It is probably the first to bring the concept of Lean Six Sigma across all the processes in the company. Which means you'll get your projects delivered on time. You will get better value considering that we maximize efficiencies and we pass the benefits on to our customers. At Sowparnika we believe in sensible pricing. Our commitment is based on the strongly grounded principles of Transparency, Customer Satisfaction and Teamwork. Our In-house competencies and trained expertise in Engineering, Design, Architecture, Structural, Project Management, Electrical, Plumbing and all other facets required to deliver large scale projects is the USP of the Organization. Due to this in-house advantage, brand Sowparnika has a unique edge while staying ahead of other players in the segment. Working in sync with the Prime Minister’s vision of “Homes for All by 2020”, Sowparnika has accelerated its pace and scaled capabilities to cater to this huge need with a particular focus in South India. We have 6000+ satisfied customers, 35+ completed projects, 35+ ongoing projects, 50+ lakh sq.ft developed, 50+ lakh sq.ft under development and a strong presence in 3 states. The Company is headquartered in Bangalore and is present across Karnataka, Kerala and Tamil Nadu. Looking forward to a long and fruitful association. 02 Volume. 01 | Issue. 05 | June. 2019

Glimpse of the month 01 02 03 04 www.sowparnika.com GOOD ENOUGH REASON TO OWN! 9 999` ,PAYJUST * YOUR INTERNATIONAL TRIP & YOUR TRIP TO GOA AND & NOTHING TILL POSSESSION PREMIUM HOME A PREMIUM HOME HTiullrr3y0!tOhfJfuenreVa2l0id19 at at *T&C Apply `9,999*/- `9,999/* - (ALL INCLUSIVE) (ALL INCLUSIVE) Choose Your Location: SARJAPUR MAIN ROAD / WHITEFIELD Choose Your Location: SARJAPUR MAIN ROAD / WHITEFIELD 05 06 07 Koorkencherry, Thrissur Amala Nagar, Thrissur OWN YOUR PREMIUM HOME & PAY JUST 1 LAKH NOW AND AVAIL Kunnamangalam, Calicut GET A SPONSORED TRIP TO MALAYSIA 1 LAKH DISCOUNT 1.5, 2 & 3 BHK Premium Homes ON YOUR APARTMENT. Near Caritas Jn., Kottayam BOOK YOUR PREMIUM HOME AT THRISSUR Book your home at Sowparnika Jazzmyna and get to earn assured rental.** 1, 2 & 3 BHK Premium Homes *T&C Apply *T&C Apply *T&C Apply 1. Now good enough reason to own a Sowparnika Home. Pay Just Rs. 9,999/- and nothing till possession. 2. Own your home at Sowparnika Pranathi at just Rs. 14,999/- and pay nothing till possession. 3. Book a Sowparnika Premium Home for Rs.9,999/- (All Inclusive) and get an international trip. 4. Book your Sowparnika Premium Home for Rs.9,999/- (All Inclusive) and get a sponsored Goa trip. 5. Book a premium home with Sowparnika at Valle, near Caritas Jn., Kottayam and get a sponsored trip to Malaysia. 6. Book a Premium Sowparnika Home at Thrissur. Pay Just Rs. 1 Lakh and avail 1 Lakh discount on your apartment. 7. Book your home at Sowparnika Jazzmyna, Kunnamangalam, Calicut and get to earn assured rental. 03 Volume. 01 | Issue. 05 | June. 2019 Glimpse of this month

Attibele, Bangalore NEW PROJECT STATUS UPDATES 1 2 3 Project Status Project Status for Unnathi Image 1 - Concreting of ramp from Upper basement to ground floor on Block-A finished. Image 2 - Ground floor slab concreting work finished for on Block-A. Image 3 - Shuttering work on Block-B for Lower Basement under progress. 04 Volume. 01 | Issue. 05 | June. 2019

Whitefield, Bengaluru 12 Project Status Image 1 - Block-B, stilt floor slab concreting finished, shuttering and steel reinforcement work under progress for Block-A. Image 2 - Concreting of side walls of UG Sump area finished. Image 3 - Block-H, soil back filling and soil levelling under 3 progress. 05 Volume. 01 | Issue. 05 | June. 2019 Project Status for Indraprastha

Off Sarjapur Rd., Bengaluru 1 2 3 Project Status Project Status for Tharangini Image 1 - Block-D East-side & West-side external wall plastering work under progress. Image 2 - Under Block-A and Block-C first coat of primer for basement under progress. Image 3 - Fixing of main doors and windows on all floors of Block-A & Block-C under progress. 06 Volume. 01 | Issue. 05 | June. 2019

Whitefield, Bengaluru 1 2 3 Project Status Image 1 - Column concreting 100% finished under Block-D and Block-E and ready for shuttering. Image 2 - Concreting of lower basement slab on Block-D finished. Image 3 - Block-C column reinforcement and shuttering work under progress. 07 Volume. 01 | Issue. 05 | June. 2019 Project Status for The Columns

Kumbalgodu, Mysore Road, Bengaluru 1 2 3 Project Status Image 1 - Under Block-B & C 80mt retaining wall has finished and shuttering of the remaining wall till stilt floor upto 2ft more under progress. Image 2 - Under Block-C 90% of column footing work and Block-E 98% of PCC work have finished. Image 3 - Shuttering of pillars on Block-C under progress. 038 Volume. 01 | Issue. 05 | June. 2019 Project Status for Pranathi

Sarjapur Road, Bengaluru 1 2 3 Project Status Project Status for Flamenco Image 1 - Block-E PCC work for column footing finished and soil back filling under progress. Image 2 - Concreting of ground floor work on Block-B finished. Image 3 - Column shuttering work under progress on F-Block. 09 Volume. 01 | Issue. 05 | June. 2019

VijaSyaarjnaapguarrR4otahdS, tBaegneg, aMluyrsuuru 1 2 3 Project Status Project Status for The Landmark Image 1 - Foot casting work for the remaining pillars is under progress. Image 2 - A view of the other area of the site. Image 3 - Foot casting and substructure works under progress. 10 Volume. 01 | Issue. 05 | June. 2019

Thrikkanapuram, Trivandrum 1 2 3 Project Status Project Status for Navarathinam Pearl Image 1 - 2nd floor block work under progress. Image 2 - 8th floor beam and slab shuttering work under progress. Image 3 - Front elevation view & 8th floor slab shuttering work under progress. 11 Volume. 01 | Issue. 05 | June. 2019

Thrikanapuram, Trivandrum 12 Project Status Image 1 - Courtyard exterior wall plastering under progress 3 for RVG-4. Image 2 - Toilet plumbing & wall chasing work under progress for RVG-5 (Total -08/95 nos finished). Image 3 - Passage plastering for 3rd floor under progress and Main floor & wall tiling under progress for RVG-5. 12 Volume. 01 | Issue. 05 | June. 2019 Project Status for River View Garden

Sreekariyam, Trivandrum 1 2 3 Project Status Project Status for Vaishnavam Image 1 - Kitchen & Duct pipe works finished. Image 2 - Courtyard handrail and plastering work under progress. Image 3 - Putty work, Primer work and Door Shutter fixing works have completed. 13 Volume. 01 | Issue. 05 | June. 2019

Peroorkada, Trivandrum 12 Project Status Image 1 - West-side balcony handrail bottom concreting and 3 plastering under progress. Image 2 - Simultaneous works are in progress of concrete works for Kitchen pedestal and filling of wall chasing gaps in toilets on 7th floor. Image 3 - East-side scaffolding removing under progress. 14 Volume. 01 | Issue. 05 | June. 2019 Project Status for Grand Square

At Palimukku Jn, Vazhayila Trivandrum 1 2 3 Project Status Project Status for West Holmes Image 1 - Raft footing work under progress. Image 2 - Lower Basement Area (North-side), Retaining wall –75% completed Image 3 - Retaining wall work on lower basement. 15 Volume. 01 | Issue. 05 | June. 2019

Thycaud, Trivandrum 12 Project Status Image 1 - Front elevation view. Image 2 - Ground Floor - Block work finished. Image 3 - Third Floor – Concreting of 2nd floor roof finished. 3 16 Volume. 01 | Issue. 05 | June. 2019 Project Status for Bhavani

Sreekaryam (Behind CET), Trivandrum 1 2 3 Project Status Project Status for Seychelles Image 1 - 33nos of Footing works completed. Image 2 - Retaining Wall –15 mts concreting finished. Image 3 - 28nos of pedestal works completed and 5 remaining. 17 Volume. 01 | Issue. 05 | June. 2019

Edappaly, Kochi 1 2 3 Project Status Project Status for Atrium Image 1 - Remaining area of Lower Basement roof slab shuttering work in progress. Image 2 - Lower Basement – Remaining retaining wall shuttering work under progress. Image 3 - Shuttering of remaining pillars in Upper Basement is under progress. 0185 Volume. 01 | Issue. 05 | June. 2019

Near Caritas Jn, Kottayam 12 Project Status for Valle Project Status Image 1 - External coat of primer finished on all sides. Image 2 - External compound wall on West-side completed & South-side in progress. Image 3 - Entrance gate and Ramp work are in progress. 3 19 Volume. 01 | Issue. 05 | June. 2019

Amalanagar,Thrissur 1 2 3 Project Status Project Status for Natura Image 1 - Concreting of GF slab is under progress on Block B. Image 2 - Concreting of GF slab floor finished (Completed on 31st May) Image 3 - Internal plastering work completed up to UBF & running on GF – Block A 20 Volume. 01 | Issue. 05 | June. 2019

Koorkencherry, Thrissur 12 Project Status for Edifice Project Status Image 1 - Concreting of the Retaining wall 40% work finished. Image 2 - 75% of the excavation and stone cuttingwork for foundation completed. Image 3 - 18% of column concreting completed for the lower basement. 3 21 Volume. 01 | Issue. 05 | June. 2019

Kunnamangalam, Calicut 1 2 3 Project Status Project Status for Jazzmyna Image 1 - Out of 161 piling pits, 142 piles have finished, pile dressing in progress. Image 2 - Remaining piling process under progress. Image 3 - Excavation for pile cap under progress. 22 Volume. 01 | Issue. 05 | June. 2019

What Sowparnika customers has to say Mr. Krishna Mohan Pathak Purple Rose I opted for Sowparnika Purple Rose as it was an affordable project, with nice infrastructure and good amenities, also we faced no problem in getting getting detailed and right information on the project by the team. Thanking you Mr. Braj Raj Purple Rose The reason I went for Sowparnika Purple Rose was it’s budget, locality and very good project. During the process I realized that coordination is excellent and the quality served is also good as promised. Thanking you 23 Volume. 01 | Issue. 05 | June. 2019 Testimonials

Mr. Souvik Sarkar Purple Rose As we have been staying at Sowparnika Sanvi and when we came across Sowparnika Purple Rose through a reference we immediately book a flat as it was affordable to buy with good facilities, and also the team was customer friendly. Overall we had a good experience with the team in buying our first home. Thanking you Mr. Suresh Nalli, Mr. Srinivasa Rao Testimonials Flamenco We finalized our individual flats with Sowparnika Flamenco and there are many points which helped us in making this choice like especially the 9,999/- scheme which they are running, with flexible payment options, locality of the project, customer service which is far better in many ways, and of course the budget. Thanking you 24 Volume. 01 | Issue. 05 | June. 2019

Few of our Mr. Shiju HAPPY CUSTOMERS Jazzmyna Mr. Mahin C.S Flamenco Mr. Rajasekar Reddy Purple Rose Mr. Roshan Kaushik Nakar Unnathi Mr. Dinesh P.S Purple Rose Mr. Ajesh A.J Mr. Sridhar Sahoo Jazzmyna Purple Rose 25 Volume. 01 | Issue. 05 | June. 2019 Some of our Happy Customers

Activities at site Karnataka YOUR INTERNATIONAL TRIP & PREMIUM HOME at `9,999*/- (ALL INCLUSIVE) Choose Your Location: SARJAPUR MAIN ROAD / WHITEFIELD 26 Volume. 01 | Issue. 05 | June. 2019 Some of our Happy Customers

YOUR TRIP TO GOA AND A PREMIUM HOME at `9,999*/- (ALL INCLUSIVE) Choose Your Location: SARJAPUR MAIN ROAD / WHITEFIELD 27 Volume. 01 | Issue. 05 | June. 2019 Some of our Happy Customers

28 Volume. 01 | Issue. 05 | June. 2019 Some of our Happy Customers

Activities at site South Kerala 29 Volume. 01 | Issue. 05 | June. 2019 Some of our Happy Customers

Activities at site Central Kerala 30 Volume. 01 | Issue. 05 | June. 2019 Some of our Happy Customers

Koorkencherry, Thrissur Amala Nagar, Thrissur PAY JUST 1 LAKH NOW AND AVAIL 1 LAKH DISCOUNT ON YOUR APARTMENT. BOOK YOUR PREMIUM HOME AT THRISSUR 93435 15152Call To Know More *T&*CT&ACppAlpyply Some of our Happy Customers 31 Volume. 01 | Issue. 05 | June. 2019

OWN YOUR PREMIUM HOME & GET A SPONSORED TRIP TO MALAYSIA Near Caritas Jn., Kottayam 1, 2 & 3 BHK Premium Homes 98476 32000Call To Know More *T&C Apply Some of our Happy Customers 32 Volume. 01 | Issue. 05 | June. 2019

Activities at site North Kerala Kunnamangalam, Calicut 1.5, 2 & 3 BHK Premium Homes Book your home at Sowparnika Jazzmyna and get to earn assured rental.** 888R0eac0h us1at1777 *T&C Apply Some of our Happy Customers The above illustration is an artistic impression and cannot be considered as representation of facts. 33 Volume. 01 | Issue. 05 | June. 2019

GOOD ENOUGH REASON TO OWN! 9 999` ,PAYJUST * & NOTHING TILL POSSESSION HTiullrr3y0!tOhfJfuenreVa2l0id19 34 Volume. 01 | Issue. 05 | June. 2019 *T&C Apply Some of our Happy Customers

35 Volume. 01 | Issue. 05 | June. 2019 Some of our Happy Customers

SOWPARNIKA AND GET REWARDED. You are an important member of the Sowparnika family and we have planned something really special for you. You can refer your friends/relatives to buy any of our Sowparnika Home and once their booking is confirmed by signing the agreement of sale, we will be rewarding your gesture as a token of our appreciation. We value you and your patronage! Kindly visit www.sowparnika.com to know about our ongoing and future projects. Karnataka South Kerala Central Kerala North Kerala 790 290 1212 98476 98479 9342 61 61 62 88800 11777 36 Volume. 01 | Issue. 05 | June. 2019 Some of our Happy Customers

--- - - - - - ---- -- -- - - - - - - - - - - - - - --------------- - - - - - - - - The Community Change Driver. SowparBee is a - -- progressive community builder for a better - India where people are inspired and motivated to live a healthy and active lifestyle and take - - - - - - - - - - - - - - - - - care of their surroundings. Sowparbee is a lively and bubbly honey bee who is our mascot for - - - - - - - - spreading happiness all around. - - - - - - - - - - - - - - - - - - - - -- -- -- - - - - - - - - - - - - - - CSR Activity After a lifetime of working, raising families and contributing to the nation in countless other ways, Senior citizens deserve respect, love and the best treatment in the society. Let’s bring joy into their lives and make them smile 37 Volume. 01 | Issue. 05 | June. 2019 SowparBee

Women’s health is of crucial importance. By providing better health services we can improve the quality of life for woman which in turn helps in empowering the them. Women Health Programmes and Seminars should be conducted to educate them about their overall health. - - - - - - - - - - - - - - - - - - Social empowerment is basically implemented at four levels: - - - - - - - - (1) The individual level - where the person values himself/herself and - - - - - - - actively wants to participate in life (2) Family level -- - - (3) Community level and ---- - - - - - - - - - - - - ------ (4) Social policy level that further - - - impacts local and national level -- - actions thus promoting social ---- - -- ---- - - - - - - - - - - equality. - SowparBee SCAN & REGISTER For more information visit our website www.sowparbee.com And also subscribe to our social handles for more updates. 38 Volume. 01 | Issue. 05 | June. 2019

Karnataka Projects On going Projects 39 Volume. 01 | Issue. 05 | June. 2019 Karnataka Projects

RERA No. PRM/KA/RERA/1250/304/PR/171208/001131 TYPE of Units BHK Homes Budigere Cross, Hoskote Area In Sq.ft Total no. of Floors Attibele, Bangalore Total no. of Units Off Sarjapur Road Budigere Cross, Hoskote 40 Volume. 01 | Issue. 05 | June. 2019 9019 222 777 Brochure | Walk Through | Floor Plans TYPE of Units BHK Homes Area In Sq.ft Total no. of Floors Total no. of Units Attibele, Bangalore 782 980 1212 Brochure | Walk Through | Floor Plans TYPE of Units BHK Homes Area In Sq.ft Total no. of Floors Total no. of Units Off Sarjapur Road, Bangalore 78478 60002 Brochure | Walk Through | Floor Plans Karnataka Projects

Vijayanagar, 4th Stage, Mysuru RERA No. PRM/KA/RERA/1250/304/PR/171024/000764 TYPE of Units BHK Homes Soukya Road, Whitefield Area In Sq.ft Total no. of Floors Sarjapur, Bangalore Total no. of Units 41 Volume. 01 | Issue. 05 | June. 2019 Vijayanagar, 4thStage, Mysuru 93796 16162 Brochure | Walk Through | Floor Plans TYPE of Units BHK Homes Area In Sq.ft Total no. of Floors Total no. of Units Soukya Road, Whitefield 9019 222 555 Brochure | Walk Through | Floor Plans TYPE of Units BHK Homes Area In Sq.ft Total no. of Floors Total no. of Units Sarjapur, Bangalore 808 844 8899 Brochure | Walk Through | Floor Plans Karnataka Projects













Kunnamangalam, Calicut TYPE of Units BHK Homes Area In Sq.ft Total no. of Floors Total no. of Units Kunnamangalam, Calicut 888 00 11 777 Scan for Jazzmyna details 48 Volume. 01 | Issue. 05 | June. 2019 North Kerala Project


Like this book? You can publish your book online for free in a few minutes!
Create your own flipbook