PrefaceThe National and Regional Load Despatch Centres (NLDC/RLDCs) were constituted as statutory bodies with theirfunctions defined under the Electricity Act 2003 and the Indian Electricity Grid Code. Initially, the RLDCs were operatedby the Central Electricity Authority, as part of the Regional Electricity Boards (REBs), since 1964. Consequent to theformation of Power Grid Corporation of India Ltd. (POWERGRID), the RLDCs were transferred to POWERGRID during1994 to 1996, in a phased manner.Ministry of Power, Government of India directed POWERGRID, vide OM dated 04th July 2008, to set up Power SystemOperation Corporation (POSOCO) as a wholly owned subsidiary of POWERGRID. The functions of POSOCO included,inter-alia, to supervise and control all aspects concerning operations of NLDC and RLDCs, act as an apex organizationfor manpower requirement of NLDC and RLDCs, to ensure planning and implementation of infrastructure required forsmooth operation and development of NLDC and RLDCs, to advise and assist the SLDCs, including for specializedtraining, etc. POSOCO was, accordingly, incorporated as a wholly owned subsidiary of POWERGRID and registered on20th March 2009. MoP, vide notification dated 27th September, 2010, notified that POSOCO shall operate the five RLDCsand NLDC w.e.f. 1st October, 2010. POSOCO has since been discharging the statutory function of power system operation,under the Act. Consequent to Gazette notification ref SO 4089 (E) dated 19th December 2016, POSOCO commencedoperation as a wholly owned Government of India company w.e.f 3rd January 2017.As a subsidiary company, the “Delegations of Power” of POWERGRID was in vogue for POSOCO. This continued duringthe initial transition phase after 03rd January 2017. After the constitution of the independent Board of Directors of POSOCOin Dec 2017, the first Executive Committee Meeting (ECM) was held on 24th Jan 2018 wherein it was unanimously decidedDoP POSOCO Page: 1

to formulate and adopt POSOCO’s own “”Delegation of Power” to discharge the statutory functions assigned toNLDC/RLDC and to realize the vision and mission of the corporation.Delegation of power (DOP) or the ‘Delegation of Authority’ (DOA) is an indispensable document for any organization.Delegation means assigning of certain responsibilities along with the necessary authority by the management of theorganization to the employees. It only means transfer of certain responsibilities to the employees and giving them therequired authority, which is necessary for the discharge of the responsibility properly. The three important elements involvedin the DOP are (i) Authority, (ii) Responsibility, and (iii) Accountability.Authority is the legal right of the management to command the employees while the responsibility relates to the duties forcompletion of the assigned task. Accountability is the obligation of the employees to carry out the duties as per standardsof performance. In an organization, authority is normally defined as the power and right of a person to use and allocate theresources efficiently, to take decisions so as to achieve the organizational objectives. Thus, Authority has to be well defined.The level of authority is commensurate with the employee’s level in the management hierarchy. Authority is alwaysaccompanied with an equal amount of responsibility.Responsibility is termed as the duty of an employee to complete the assigned tasks. Responsibility usually comes withadequate authority. In case there is inadequate authority then it leads to discontent and dissatisfaction amongst theemployees. Responsibility gives a sense of accomplishment on successful completion of the job.Accountability means being answerable for the end result. It arises from responsibility. Accountability makes the employeeto be innovative and more focused on job completion.DoP POSOCO Page: 2

POSOCO being a knowledge based company, ‘human resources’ and ‘decision support system’ are its major assets.POSOCO would have a very modest capital expenditure and the functional powers delegated to its employees would becritical than the financial powers. The load despatching function of NLDC/RLDCs is perceived as a ‘mission critical activity’for uninterrupted and reliable power supply; a ‘facilitator’ for an efficient electricity market; an ‘optimizer’ of precious powergenerating resources; an ‘instrument’ for equitable and fair use of the available transmission infrastructure and an‘indispensable link’ between the managers, administrators, planners and regulators on one end and the physical system onthe other end. NLDC/RLDCs play a major role in facilitation and deployment of renewable energy sources, achievingeconomy & efficiency and minimizing carbon footprints through despatch decisions. POSOCO has to manage the Grid inaccordance with the CERC regulations and technical standards notified by CEA. While discharging its responsibilityPOSOCO has to be transparent, neutral, fair and non-discriminatory towards all the entities and market players.The “Delegation of Power” for POSOCO has been formulated to keep the above distinguishing feature of POSOCO. TheDOP consists of two partsPart-1 ---- Functional Delegation of PowerPart-2 ---- Financial Delegation of PowerThe functional DOP has been derived from the critical decision steps listed in the Standard Operating Procedure (SOP).Effort has been made to establish a ‘maker’ and ‘checker’ for each decision step and to delegate powers to an executive ofadequate level. Any imprudent assessment of a situation and inference thereof on the part of an employee can have aDoP POSOCO Page: 3

serious repercussions for the power system and electricity market beside commercial implications for stakeholders.Therefore Part-1 of the DOP is more crucial in case of POSOCO.Part-2 of the DOP covers the financial power delegated to the executives of POSOCODoP POSOCO Page: 4

POWER SYSTEM OPERATION CORPORATION LIMITED DELIGATION OF POWER Table of ContentsPreface ........................................................................................................................................................................................................................... 1FIRST TIME CHARGING................................................................................................................................................................................................... 8 A Pre Charging Activity of elements within Region ................................................................................................................................................... 8 B Post Charging Activity of elements within region................................................................................................................................................... 8 C Pre Charging Activity for Inter Regional elements.................................................................................................................................................. 8 D Post Charging Activity for Inter Regional elements................................................................................................................................................ 9 E Transnational Element Charging, Trial Operation & Certification .......................................................................................................................... 9 F Post Charging & Certification* .............................................................................................................................................................................. 10Open Access Approval ................................................................................................................................................................................................. 12 Registration of Utility ............................................................................................................................................................................................... 12 Registration of Non-Trader / Trader Applicant........................................................................................................................................................ 12 Application Processing ( Advance & FCFS) by MO Dept. ......................................................................................................................................... 12 Application Processing ( Day ahead & Contingency) by Real time control room Shift officials .............................................................................. 12 Modification/Updates of STOA Rates ...................................................................................................................................................................... 13 Issuance of quarterly NOC to Regional entities ....................................................................................................................................................... 13 Invoking Regulatory Measures ................................................................................................................................................................................ 13Update SCADA database and add new diagrams with commissioning of new element............................................................................................. 14 A. Pre Charging......................................................................................................................................................................................................... 14 B. Post Charging ....................................................................................................................................................................................................... 14Availability of SCADA system ....................................................................................................................................................................................... 15DoP POSOCO Page: 5

Processing of SCADA upgradation/replacement contract (AMC)................................................................................................................................ 15Testing of Backup Control Centre for SCADA functionality ......................................................................................................................................... 16Procedure to compute Total Transfer Capability(TTC)/ Available Transfer Capability(ATC)....................................................................................... 17for Inter-Regional corridors ......................................................................................................................................................................................... 17Procedure to compute Import /Export Transfer Capability of ................................................................................................................................... 18State/ individual Control areas .................................................................................................................................................................................... 18DoP POSOCO Page: 6

DELIGATION OF POWER (FUNCTIONAL AREA)DoP POSOCO Page: 7

FIRST TIME CHARGINGSl.No Nature of Power Authority Extent of Remarks Power A Pre Charging Activity of elements within Region1 Processing of application from Utility/Generating Co./STUsa Issuance of Format-II Dy.Manager/Manager(RLDC)(Acknowledgement of proposal).b Approval for charging and Trial Ch.Manager/DGM(RLDC) Full Power *NLDC consent to beRun as per Format-IV. up to 400kV taken for HVDC & Level of EHVAC elements EHVAC charged at a higher voltage level (more than 400 kV) B Post Charging Activity of elements within region1 Processing of request for issuance of Trial Operation Certificate from Utility/Generating Co./STUsa Issuance of Trial Operation Head of RLDCs (ED/GM) Full Power * WithCertificate for the element recommendation of HoD of FTC Dept. C Pre Charging Activity for Inter Regional elements1 Processing of application from Utility/Generating Co./STUsa Issuance of Format-II Dy.Manager/Manager(RLDC)(Acknowledgement of proposal).DoP POSOCO Page: 8

b Forwarding Proposal for First Ch.Manager/DGM(RLDC) Full Power Time Charging of Element of Full Power respective portion for the region to NLDC for approvalc Approval for Charging and Trial DGM/AGM (NLDC) Run as per Format-IV by NLDC D Post Charging Activity for Inter Regional elementsProcessing of request for issuance of Trial Operation Certificate from Utility/Generating Co./STUsa Forwarding verified post Chief Manager/DGM Full Powercharging documents & relevantdata for the portion of theelement belonging to respectiveregion to NLDCb Issuance of Trial Operation Head of NLDCs (ED/GM) Full PowerCertificate for the element byNLDC E Transnational Element Charging, Trial Operation & Certification1 Pre-Charginga Issuance of Format-II Dy.Manager/Manager(Acknowledgement of proposal). (RLDC)b Forwarding proposal for First Ch. Manager/DGM Full PowerTime Charging of Element of (RLDC)respective portion (in Indianterritory) to NLDC for approvalDoP POSOCO Page: 9

c Approval for Charging and Trial Head of NLDCs (ED/GM) Full Power Run as per Format-IV by NLDC F Post Charging & Certification*a Forwarding verified post Chief Manager/DGM(RLDC) Full Powercharging documents & relevantdata for the portion of theelement belonging to respectiveregion to NLDCb Issuance of Trial Operation Head of NLDCs (ED/GM) Full PowerCertificate for the part of theelement (in Indian Territory) byNLDCc *For the portion out of Indian Head of NLDCs (ED/GM) Full PowerTerritory NLDC with coordinatewith the NLDC of neighbouringcountry for trial operationcertificationDoP POSOCO Page: 10

The DoP Under ConsultationDoP POSOCO Page: 11

Open Access ApprovalSHORT TERM OPEN ACCESS Approval as per CERC’s OA Regulation 2008 and any amendment thereof /Procedures1. Registration of Utilitya Approval of Registration of Utility after Sr.Engineer Full Powerscrutiny of all documents Dy.Manager2. Registration of Non-Trader / Trader Applicanta Approval of Registration of Non- Dy. Manager Full Power * With intimation to FinanceTrader / Trader Applicant after scrutiny /Manager Dept. of RLDC.of all documentsb Advice to Bank for opening sub bank Dy. Manager /Manager Full Power * With intimation to Financeaccount in the name of new Applicant Dept. of RLDC.registered.3 Application Processing ( Advance & FCFS) by MO Dept.a Scrutiny of application and approval of Engr/Sr Engr. Full PowerSTOA transactionsb Rejection of STOA applications Dy.Manager/Manager Full PowerC Consent to other RLDCs where other Engr/ Sr Engr. Full PowerRLDCs are NodalD Approval of downward revision request Engr/ Sr Engr. Full Power4 E-bidding for Advance applications in case of congestiona Approval for processing of e-bidding CM/DGM Full Power5 Application Processing ( Day ahead & Contingency) by Real time control room Shift officialsa Scrutiny of application and approval of Engr/Sr Engr. Full PowerSTOA transactionsb Rejection of STOA applications Shift Incharge Full Power (CM/DGM)C Consent to other RLDCs where other Engr/ Sr Engr. Full PowerRLDCs are NodalDoP POSOCO Page: 12

6 Modification/Updates of STOA Ratesa Update the NEW STU/SLDC Rates as CM/DGM Full Powerper SLDC Letterb Update the POC Rate and Zone as per Sr Engr./Dy. Manager Full PowerQuarterly CERC POC Order7. Issuance of quarterly NOC to Regional entitiesa Issuance of NOC to Regional entities CM/DGM Full power8 Invoking Regulatory Measuresa Invoking Regulatory measures under CM/DGM Full power Regulation 19 of OA Regulation by denying access to a OA Applicant/ CM/DGM Full power *with prior intimation to Head Utility for STOA of RLDCb Invoking Regulatory measures under Regulation 25A of OA Regulation by denying access to a OA Applicant for STOADoP POSOCO Page: 13

Update SCADA database and add new diagrams with commissioning of new elementSr.No. Nature of Activity Authority Extent of Remarks Power A. Pre Charging Receipt of information – a) SLD Sr. Engr.1 b) communication infrastructure c) coordinate for appropriate infrastructure suitable for telemetry and voice communication2 Preparation and sharing of signal list and configuration details to Sr. Engr site a) Updation of database in RLDC SCADA– i) Substation ii) RTU Historian database update and addition3 iii) Protocol configuration Sr. Engr. of points in daily reports iv) ICCP Full Power v) EMS b) Intimation of database updates to NLDC and concerned SLDC4 Testing of communication link Sr. Engr.5 Preparation of SCADA display Sr. Engr.6 Point to Point checking of telemetry both digital and analog Sr. Engr. signals Sr. Engr. CM/DGM7 Receipt of FTC documents for charging clearance8 Intimation of SCADA consent (Archived for documentary evidence of KPI 72) B. Post Charging1 Receipt of C form from FTC coordinator Sr. Engr.2 Verification of SCADA data (post charging) Sr. Engr.3 Issuance of confirmation status CM/DGM Full PowerDoP POSOCO Page: 14

Availability of SCADA systemSr.No. Nature of Activity Authority Extent of Remarks 1 Checking of Daily server availability reports Power 2 Entry of day-wise availability figure in KPI portal (Quarterly) Sr. Engr. 3 Updation of monthly status on WRLDC website Sr. Engr. Full Power 4 Issuance of Documentary evidence for CERC KPI Sr. Engr. Ch. Manager / DGM Processing of SCADA upgradation/replacement contract (AMC)Sr.No. Nature of Activity Authority Extent of Remarks Power Sr. Engr.1 Verification of Daily routine check sheets provided by contractor Sr. Engr.2 Verification of Quarterly backups and Preventive maintenance activity done by contractor Sr. Engr. CM/DGM3 Logging of issues in complaint portal Sr. Engr. Sr. Engr.4 Issuance of Availability computation as per contract provisions Sr. Engr. Ch. Manager /5 Receipt of Quarterly Invoice from vendor DGM6 Verification of invoice7 Preparation of RA bill8 Recommendation for release of payment to FinanceDoP POSOCO Page: 15

Testing of Backup Control Centre for SCADA functionalitySr.No. Nature of Activity Authority Extent of Remarks Power1 Ensure availability of updated database at Backup Control Sr. Engr. Centre2 Intimation of backup testing schedule to control room Ch. Manager / DGM3 Fail over of SCADA functionality from Main Control center to Sr. Engr. Backup Control centre Verification of SCADA functionality check list a) All telemetry4 b) Important real time calculations Sr. Engr. c) Displays d) SCADA functionalities5 Verification of resolution of discrepancies found in previous Sr. Engr. report6 Restoration of SCADA functionality from Backup Control Centre Sr. Engr. to Main Control Centre7 Preparation of Test Report along with action plan for resolution Sr. Engr. of discrepancies8 Follow up of the action plan (to be verified during next testing) Sr. Engr.9 Verification and issuance of test report CM/DGMDoP POSOCO Page: 16

Procedure to compute Total Transfer Capability(TTC)/ Available Transfer Capability(ATC) for Inter-Regional corridorsS Time line Responsibility/ RemarksNo Activity Authority 1. When LGBR is not available for m+3 month, Prepration of Peak & Off Peak cases for three Engineer/Sr. last year SCADA data Engineer and PSP report for same month ahead (M+3) :- month is used considering Dy. Manager/ percentage annual growth a) Network Elements updation-transmission and Manager in demand. Engineer / 2. Present status of1 generation elements added in grid. - generation is also - Sr. Engineer considered while b) Demand- Projected demand of States-As per Engineer/Sr. preparing base cases. Engineer NLDC WRPC LGBR Report DoP c) Generation-Units under planned shutdown for the Through e-mail month(M+3)- As per WRPC LGBR Report d) Inter-regional flow provided by NLDC2 Review and approval of Peak and Off-Peak case prepared for M+3 month3 19th of every Sending the reviewed case to NLDC month Stitching the cases after receipt of all the cases from4 all RLDCs and preparing All India peak and off-peak cases for M+3 month5 Sending of All India Peak & Off Peak to all the RLDCs 24th of every NLDC month Engineer/Sr.6 Simulations done for TTC computations and identifying Engineer constraint between regions7 Updation of LTA/MTOA as per CTU approvals8 Approval of simulations and Final Declaration of TTC 26th of every Reliability /ATC for STOA/PX market month Coordinator (CM/DGM) DoPDoP POSOCO Page: 17

Procedure to compute Import /Export Transfer Capability of State/ individual Control areasSN Work Responsibility/ Tme -Line Authority Remarks Base Case is prepared with following inputs:1 1. Peak and offpeak cases prepared on M+3 Monthly Engineer/Sr. basis. Engineer 2. New elements addition in grid till date Studying various contingencies wrt: Engineer/Sr. Engineer2 1. Change the generation as per MOD Engineer/Sr. 2. Change demand in different zones of the state. Engineer Identifying most credible contingencies based : Reliability Import /Export capability3 a) N-1 of parallel transmission line/ICT Coordinator is identified when the (CM/DGM) system is N-1 complaint b) Voltage and angular limit Reliability for the severe Coordinator contingencies studied.4 Approval of study results and sending TTC/ATC (CM/DGM) of state control areas to NLDC/SLDC DGM/ AGM DoP5 Declaration of import/export capability for NLDC DoP STOA/PX in website in coordination with NLDC DoP6 Creating bid area for Power exchange transactionsDoP POSOCO Page: 18

DOP for RLDC fees & Charge Process 1. Registration of Users Activity Responsibility/Authority Extent of Remarks Power Receipt of Registration fees for new Users in RLDC1 fees & charge Collection account as per regulation Chief Manager/DGM for commencement of Grid access and intimation to FTC group. 2. Issuance of Bill Activity Responsibility/Authority Extent of Remarks Power Verification of input data for preparation of bill for different category of Users like transmission lines1 length added into grid, installed capacity of Chief Manager generating units/Seller including the start up power, allocation for Distribution Licensee /Buyer in web based fees & charge software module. Notification of Monthly RLDC fees & charge Bill to all2 users through web based software module on first DGM working day of the month 3. Collection of RLDC fees & charge payment from all Users Activity Responsibility/Authority Extent of Remarks Power Receipt of payment from Users within the stipulated Chief Manager Flashing of Debtor details if1 time as per regulation and verification of Rebate & any to higher Authorities for monthly bills after 60 days TDS amount (if applicable) deducted by Users. with surcharge calculation. 4. Quarterly Reconciliation Activity Responsibility/Authority Extent of Remarks Power1 Issuance of Quarterly reconciliation statement to all DGM RLDC fees & charge UsersDoP POSOCO Page: 19

5. Yearly Truing up by 30th Sept Activity Responsibility/Authority Extent of Remarks Power1 Approval of Truing up proposal GM/ED2 Settlement of Truing up liability with all fees & charge DGM Issuance of letter for Users by 30th Sept intimation to all Users regarding the Truing up liability towards fees & charges.DoP POSOCO Page: 20