Replaced refractory bricks in Primary –F04201

ISO 9001:2015 PROJECT PHOTOS BLASTING – PAINTING - COATING

Blasting and Painting for structures and equipment - 2016 - PVCFC

Blasting and Painting for pipe racks and equipment – 2017, 2018 - PVCFC

Blasting and Painting for pipe racks - PVCFC

Hot zinc spray coating for steel structures at Our work shop

WRAPPING FOR UNDERGROUND PIPELINE -2015 NGHI SON REFINERY PROJECT

WRAPPING FOR UNDERGROUND PIPELINE -2015

Wrapping Chan May’s Jetty legs

POWDER COATING PRODUCT

ISO 9001:2015 PROJECT PHOTOS INSULATION

Insulation installation for pipeline – Tam Dao 05

Insulation installation for Pipeline and Fittings - PVCFC

Insulation installation for turbine using concrete 2016, 2018 -PVCFC Insulation Jacket for steam turbine PVCFC

ISO 9001:2015 PROJECT PHOTOS MAINTENANCE & REPAIR STATIC AND ROTATING EQUIPMENTS

TURNAROUND 2015 - PVCFC

Disassemble and Assemble high pressure equipment 2015 – Turnaround – PVCFC

TURNAROUND 2016 - PVCFC

Centrifugal Pump disassemble and maintenance 2016 - PVCFC

Replace packing for CO2 absorber/stripper – Turnaround 2016 PVCFC

Replace packing for CO2 absorber/stripper – PVCFC

Repair – replace tank’s bottom 2017- PVCFC

Maintenance, blasting, painting and Cladding for blower - PVCFC

Cladding inside damper - PVCFC

Fabricate and replace Flexible joints for air ducts - PVCFC

Repair maintain heat exchangers/ high pressure equipment 2017- PVCFC

Repair burner distribution panel for secondary reformer 2018 – PVCFC

Maintenance and Cleaning for tank and special equipment – Vietsovpetro

Maintenance Oil separator skid

Maintenance and repair drilling tower - Vietsovpetro

Unloading/Loading Catalyst for Heat Exchanger - PVFCCo

Unloading/Loading Catalyst for HTER - PVFCCo

Maintenance Reactor R5002 – PVFCCo 2018, 2019

Remove stud-bolts of flange 18” 1500#, Replaced lip seal

Re - installation Spools, Flange – Tightening bolts

Removed Studbolts and Blind Flange BOILER –E 5000 –2018, 2019 -PVFCCo

Replace Diaphragm gasket

REMOVED SPOOLS, HEAD COVER & TUBE BUNDLE HTER –PVFCCo -2018, 2019

Transferred From Shell to Transport Container

Lift down and transferred to Vung Tau’s Work Shop for Repair

TRANSFERRED TO BACK PHU MY FERTILIZER PLANT FOR RE - INSTALLATION Repair HTER - PVFCCo

Repair Tube Bundle of HTER at workshop Cutting the Head of Transport Container by grinding machine

Repair Tube Bundle of HTER at workshop Inspection and cutting Parts of deformation

Repair Tube Bundle of HTER at workshop

Repair Tube Bundle of HTER at workshop

Re-install tube bundle of HTER

Repair HTER - PVFCCo

Installation Top Cover HTER & Tightening Bolts

Repair HTER Team

ISO 9001:2015 PROJECT PHOTOS OFFSHORE