APPENDIX A. STAPLEE PROJECTS EVALUATION FORM B. COUNCIL STRATEGIC PRIORITIES FUTURE PROJECTS MAPS Page 45

Page 46

Page 47

US 98 Underground Utilities Underground Utilities Segments A. 2,600 ft. – $1,348,000  B. 2,850 ft. – $9,620,500 C. 1,565 ft. – $9,687,500 D. 2,800 ft. – $17,727,800 TOTAL COST: $38,383,800 Fairpoint/Shoreline Multi-Use Path Total Cost: $4,729,681 Design Cost: $629,681 Page 48

Implementation of Master Plan Cost: $2,500,000 Catalyst Sites: A. Town Center  B. East Gate  C. Bay Bridge Landing Page 49